Circular of the National Development and Reform Commission on the price policy of PV power generation projects in 2018

Views : 175
Date Posted : 2018-02-28

National Development and Reform Commission on the 2018

Notice on the price policy of PV power generation project

 

Change Price regulation (2017)2196 number

Provinces, autonomous regions and municipalities, development and Reform Commission, Price Bureau, Energy Bureau, Poverty Alleviation Office, State Grid Company, Southern power grid company, Inner Mongolia Electric Power Company:

In order to implement the Energy Development Strategy Action Plan of the State Council (2014-2020), the requirements of the gradual Xianpo of new Energy Benchmarking, guide the new Energy investment rationally, promote the healthy and orderly development of photovoltaic power generation industry, decided to adjust the 2018-year PV power grid benchmarking policy. The state energy Agency for Business is hereby notified as follows:

新疆11选5First, according to the current PV industry technology progress and cost reduction, reduce the January 1, 2018 after the operation of photovoltaic power station benchmarking grid Price, Ⅰ class, Ⅱ class, Ⅲ category, the benchmark grid price adjustment for each kwh 0.55 yuan, 0.65 yuan, 0.75 yuan (including tax). Since 2019, all PV projects included in the annual scale management of financial subsidy have been executed according to the time of operation.

Second, after January 1, 2018, the adoption of "spontaneous use, margin access" mode of distributed photovoltaic power generation projects, full electric power subsidy standard reduced by 0.05 yuan, that is, the subsidy standard adjusted to 0.37 yuan per kilowatt hour (including tax). The use of "full access" mode of distributed photovoltaic power generation projects according to the location of the PV power station price implementation. All kinds of government funds and additional, system standby capacity fees and other related service charges levied on the electricity price of the distributed photovoltaic power Generation project.

Third, the village-level photovoltaic power station (0.5 MW and below) benchmarking price, household use of distributed photovoltaic projects to reduce the degree of electricity subsidy standards remain unchanged.

新疆11选5Four, the new energy generation enterprises and power grid enterprises must be true and complete record and preservation of related power generation projects on the Internet transactions, prices and subsidies, and other information, receive supervision and inspection by the relevant departments, and monthly 10th before the relevant data submitted to the National Renewable Energy Information Management Center. Price authorities at all levels should strengthen the supervision of the implementation of new energy tariff and the payment of additional subsidy for electricity price, and urge the relevant policies on Internet pricing to be implemented in place.

Five, encourage local according to the relevant provisions of the country to carry out photovoltaic power generation near the cost of distribution reform and market-oriented bidding pricing pilot, gradually improve the market to find the price mechanism.

新疆11选5The above provisions have been implemented since January 1, 2018.

2018 National PV Grid electricity price list. pdf